Licence history:
1989: Licence awarded (3rd Round)
1990: Acquisition and reprocessing of 769 km 2D seismic (NH90C)
1995: Acquisition of 182 km2 3D seismic
1996: Syd Arne declared commercial
1996: Project sanction for Phase I development
1999: First Oil
2001: Phase II development
2005: 4D seismic acquisition no. 1
2010: Phase III Development
2011: 4D seismic acquisition no. 2
2014: OBS data acquisition (Seismic acquired at the seabed)
2016: Phase III Stage 1 & 2-development completed
2016: Award of 20-year extension of 7/89
2047: Expiry of production licence on 17th February
Licence group:
INEOS E&P A/S (Operator) 36,78930%
Ineos Energy (Syd Arne) ApS 61,51572%
Danoil Exploration A/S 1,69498%
Licence area: 93.3 km2
Development
Syd Arne platform including processing plant, storage tank, gas pipeline to Harald, buoy loading of oil, and 20 well slots
SAE, wellhead platform with 12 well slots
SAN, wellhead platform with 12 well slots
Bridge from the Syd Arne platform to SAE
Pipeline from SAE to SAN
Production wells:
Syd Arne: 13 producers, 7 water injectors, 1 P&A
SAE: 4 producers
SAN: 5 producers, 2 water injectors